23 September 2013
Library Refurbishment, Phase 2 - Decorators are now in!
As you can see from the photographs, taken by our contractors Overbury, decorating has begun! To maintain the colour theme throughout the library, the 2nd and 3rd floors will also have feature walls in the now familiar orange, red and pink.
Both floors will have new grey carpet which we hope will cope with the extensive footfall expected over the years.
To see the latest photographs of the study rooms on floor 2, the flexible teaching spaces and the roof plantroom ready for action, please view the Aston University Library Flickr account
Kind Regards
Library Photography Team
Kerstin, Nicola and Val
Tags:
2013,
phase 2,
refurbishment
30 August 2013
Library Refurbishment, Phase 2 - Drilling continues
The refurbishment work continues apace and the drilling has recommenced with vigour! However, the library staff are soldiering on and you will be pleased to know that we are working hard on ordering reading list material, ensuring all online readings are available, planning library welcome sessions and teaching seminars for the start of term.
If you are struggling to study with the building noise, you may find it quieter in the following places MB606 (80 spaces) and MB 5th Floor study area (60 spaces). Also, the social study areas on the landings near the sky-lifts on each floor of the Main Building.
As always the latest refurbishment photographs are available on Flickr
Kind Regards
Library Photographic Team
Kirsten, Nicola and Val
Tags:
phase 2,
refurbishment
9 August 2013
Library Refurbishment, Phase 2 - 2nd and 3rd floor progress
The latest photos show the arrival of the conductors and the crane lifting them in place on the top of the Library roof.
The different study areas are now starting to take shape on the 2nd and 3rd floors including the Flexible Group Study Rooms. To view all the latest refurbishment photographs please take a look at our Flickr page
Kind Regards
The Library Photography Team
Kerstin, Nicola and Val
Tags:
phase 2,
refurbishment
2 August 2013
Library refurbishment, Phase 2 - machines take over
There are no new photos of the refurbishment progress this week. However, everything seems to be running to schedule. Views of the contractor's base, behind the library, show a huge supply of plasterboard and ducting, which has been moving up to 2nd and 3rd floors in the external lift.
To the view the refurbishment photographs so far please access our Flickr site
Kind Regards
The Library Photography Team
Kerstin, Nicola and Val
Tags:
phase 2,
refurbishment
24 July 2013
Library Refurbishment, Phase 2 - New photos
![]() |
Floor 2 - Raised floor installed |
![]() |
Floor 3 - Stripping out the brickwork |
If you would like to view more of the photographs please view our Library Flickr page.
Kind Regards
Library Photography Team
Kerstin, Nicola and Val
Tags:
2013,
phase 2,
refurbishment
21 June 2013
Library Refurbishment, Phase 2 - 2nd and 3rd Floors are now empty!
Latest Photos and Videos
The Library Office windows overlook the Health Clinics car park and Library Staff were treated to a first hand view of large panes of glass being removed from the 2nd and 3rd floors. It was windy and raining but each pane of glass was transported safely. The main Library Office window is now a mosaic of scaffolding and planks of wood but everything is in place for the builders to start transporting their supplies up to the 3rd floor next week.
The 2nd and 3rd floors are now clear. All the books, shelving, computers, printers, tables and chairs have been moved and all that is left is the infamous green carpet, dust and the odd revision note from times gone by. The builders will start work next week so be prepared for a bit more noise.
Just a reminder that you now need to look for books on the 1st Floor and Ground Floor of the Library. The shelf numbers start from 001-531 on the 1st floor (includes LAW REF) and from 532-900 on the Ground Floor.
Please note don't rely on our library catalogue records for the moment as they will need to be updated. We will let you know when this has happened but in the meantime if you can't find a book please speak to a member of staff at the Library Help Desk.
Check out the latest photos on Flickr
The Library Photography Team
Kerstin, Nicola and Val
The Library Office windows overlook the Health Clinics car park and Library Staff were treated to a first hand view of large panes of glass being removed from the 2nd and 3rd floors. It was windy and raining but each pane of glass was transported safely. The main Library Office window is now a mosaic of scaffolding and planks of wood but everything is in place for the builders to start transporting their supplies up to the 3rd floor next week.
The 2nd and 3rd floors are now clear. All the books, shelving, computers, printers, tables and chairs have been moved and all that is left is the infamous green carpet, dust and the odd revision note from times gone by. The builders will start work next week so be prepared for a bit more noise.
Just a reminder that you now need to look for books on the 1st Floor and Ground Floor of the Library. The shelf numbers start from 001-531 on the 1st floor (includes LAW REF) and from 532-900 on the Ground Floor.
Please note don't rely on our library catalogue records for the moment as they will need to be updated. We will let you know when this has happened but in the meantime if you can't find a book please speak to a member of staff at the Library Help Desk.
Check out the latest photos on Flickr
The Library Photography Team
Kerstin, Nicola and Val
Tags:
phase 2,
refurbishment
14 June 2013
Library Refurbishment Phase 2, 2013 - Book move completed!
Latest Photos and Videos
A team of Library Staff have been working hard over the weekend to erect shelving on the Ground Floor to accommodate the books from the 3rd Floor. They were so fast that on Monday morning we were ahead of schedule. By Wednesday the book move had been completed two days ahead of schedule. You now need to look for books on the 1st Floor and Ground Floor of the Library. The shelf numbers start from 001-531 on the 1st floor (includes LAW REF) and from 532-900 on the Ground Floor.
Please note don't rely on our library catalogue records for the moment as they will need to be updated. We will let you know when this has happened but in the meantime if you can't find a book please speak to a member of staff at the Library Help Desk.
Our non-active stock is being moved to storage and the Library shelving is now being dismantled on the 2nd and 3rd Floors. Furniture is being donated to charity, stored by the University or may even end up as a souvenir!
Check out the latest photos on Flickr
The Library Photography Team
Kerstin, Nicola and Val
A team of Library Staff have been working hard over the weekend to erect shelving on the Ground Floor to accommodate the books from the 3rd Floor. They were so fast that on Monday morning we were ahead of schedule. By Wednesday the book move had been completed two days ahead of schedule. You now need to look for books on the 1st Floor and Ground Floor of the Library. The shelf numbers start from 001-531 on the 1st floor (includes LAW REF) and from 532-900 on the Ground Floor.
Please note don't rely on our library catalogue records for the moment as they will need to be updated. We will let you know when this has happened but in the meantime if you can't find a book please speak to a member of staff at the Library Help Desk.
Our non-active stock is being moved to storage and the Library shelving is now being dismantled on the 2nd and 3rd Floors. Furniture is being donated to charity, stored by the University or may even end up as a souvenir!
Check out the latest photos on Flickr
The Library Photography Team
Kerstin, Nicola and Val
Tags:
phase 2,
refurbishment
6 June 2013
Library Refurbishment Phase 2, 2013 - Clearing the floors
Phase 2 of the Library Refurbishment has begun! Some of you studying in the Library may have already witnessed staff moving books from the 2nd Floor and reshelving them on the 1st Floor. There are a number of offices, cupboards and teaching rooms which are being cleared including our Library Plant Room situated on the 3rd Floor. Staff are working this weekend to erect shelving on the Ground Floor so that we will be ready to start moving 3rd Floor books next week. We are documenting our refurbishment with photographs that are being uploaded regularly to Flickr. Please view our latest montage at http://www.flickr.com/photos/lis_refurb/collections/
Library Refurbishment Photography Team
Kerstin, Nicola and Val
Library Refurbishment Photography Team
Kerstin, Nicola and Val
Tags:
phase 2,
refurbishment